Tuesday, January 26, 2010

Build-Out Plans

We submitted our plans to the city last Thursday. The timeline for the plans to be back in our possession is 10 days from submittal. We are hoping that there is not going to be too many changes needed to the plans. Since this is a new venture into the city, things could get tricky. The many changes and details that were made to the plans prior to submittal should help with the process. The timing of the build-out plans, Health Department plans and ABC license seems to be on a collision course. They should all be approved within two weeks of each other. It is funny that even though I read various blogs and talked to many brewers, the timeline for the opening seems to be what everybody mentioned. "Take your projected opening date and add five to six months to that". Our initial opening date was sometime in September 2009. It looks like we are in-line to open in the month of March 2010. With much luck, it will be worth the wait.

No comments:

Post a Comment